Respass Corporation has provided the following data concerning an investment project that it is considering: Initial investment $ 160,000 Annual cash flow $ 54,000 per year Salvage value at the end of the project $ 11,000 Expected life of the project 4 years Discount rate 15% Click here to view Exhibit 14B-1 and Exhibit 14B-2, to determine the appropriate discount factor(s) using the tables provided. The net present value of the project is closest to:

Respuesta :

Answer: $516

Explanation:

Net Present value is the present value of inflows less present value of outflows.

The project has annual inflows of $54,000 except in 4th year where it will have inflows of $65,000 because the salvage value will be added to the inflows.

Present value of inflows = 54,000/1.12 + 54,000/1.12² + 54,000/1.12³ + 65,000/1.12⁴

= $160,516

Net Present Value = 160,516 - 160,000

= $516