It would be 16 men.
Step-by-step explanation:
Let the number of men dig a pond in 6 day be x. Then,
It is a case of inverse variation.
12 × 8 = 6x
=> 96 = 6x
=> x = 96/6
=> x = 16
Hence, 16 men can dig a pond in 6 days.
Answer:
Answer is 16…..
12 men take 8 days for digging a pond, so we use simple method to solve this problem.
We multiple the both things that is 12 and 8 then get 96 is the result which is equal to multiple of 6 days and ?Men then get 16 men