Teller Co. is planning to sell 900 boxes of ceramic tile, with production estimated at 870 boxes during May. Each box of tile requires 44 pounds of clay mix and 1/4 hour of direct labor. Clay mix costs $0.40 per pound and employees of the company are paid $12.00 per hour. What is the total amount to be budgeted for direct labor for the month? $2,610 $10,440 $2,700 $41,760

Respuesta :

Answer:

The correct answer is $2,610.

Explanation:

According to the scenario, computation of the given data are as follow:-

We can calculate the the direct labor cost by using following formula:-

Direct labor hour required= Estimated production × Direct labor hour

= 870 × 1÷4 =217.5 hours

Direct labor cost = Direct required labor hour × Rate of labor per hour

= 217.5 hours × $12

= $2,610

According to the analysis, $2,610 is the total amount to be budgeted for direct labor.